Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Pearson PMI-100 New Attempt

Page: 16 / 26
Total 704 questions

Certified Associate in Project Management (CAPM)® Questions and Answers

Question 61

The purpose of the Project Communications Management Knowledge Area is to:

Options:

A.

Monitor and control communications throughout the entire project life cycle.

B.

Maintain an optimal flow of information among all project participants.

C.

Develop an appropriate approach for project communications.

D.

Ensure timely and appropriate collection of project information.

Question 62

The following is a network diagram for a project.

The free float for Activity H is how many days?

Options:

A.

4

B.

5

C.

10

D.

11

Question 63

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

Options:

A.

appetite

B.

tolerance

C.

threshold

D.

management

Question 64

The three processes of Project Cost Management are:

Options:

A.

Estimate Costs, Control Schedule, and Control Costs.

B.

Estimate Costs, Determine Budget, and Estimate Activity Resources.

C.

Determine Budget, Control Schedule, and Estimate Activity Resources.

D.

Estimate Costs, Determine Budget, and Control Costs.

Page: 16 / 26
Total 704 questions