Question 53

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Question 54

The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:

Options:

A.

exploit

B.

avoid

C.

mitigate

D.

share

Question 55

The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:

Options:

A.

Earned value management.

B.

Forecasting.

C.

Critical chain methodology.

D.

Critical path methodology.

Question 56

Which Process Group includes the Manage Stakeholder Engagement process?

Options:

A.

Executing

B.

Planning

C.

Monitoring and Controlling

D.

Initiating