Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Last Attempt PMI-100 Questions

Page: 21 / 26
Total 704 questions

Certified Associate in Project Management (CAPM)® Questions and Answers

Question 81

After Define Activities and Sequence Activities, the next process is:

Options:

A.

Estimate Activity Resources.

B.

Estimate Activity Durations,

C.

Develop Schedule.

D.

Control Schedule.

Question 82

Which baselines make up the performance measurement baseline?

Options:

A.

Scope baseline, cost baseline, and schedule baseline

B.

Scope baseline, project management baseline, and quality baseline

C.

Cost baseline, schedule baseline, and risk baseline

D.

Cost baseline, project management baseline, and schedule baseline

Question 83

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Question 84

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Page: 21 / 26
Total 704 questions