Winter Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

CAPM PMI-100 Book

Page: 3 / 26
Total 704 questions

Certified Associate in Project Management (CAPM) Questions and Answers

Question 9

The only Process Group that comprises processes that typically occur from the beginning to the end of the project life cycle is:

Options:

A.

Planning.

B.

Executing,

C.

Monitoring and Controlling.

D.

Closing.

Question 10

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Question 11

Which input to the Manage Stakeholder Engagement process is used to document changes that occur during the project?

Options:

A.

Issue log

B.

Change log

C.

Expert judgment

D.

Change requests

Question 12

Typical outcomes of a project include:

Options:

A.

Products, services, and improvements.

B.

Products, programs, and services.

C.

Improvements, portfolios, and services.

D.

Improvements, processes, and products.

Page: 3 / 26
Total 704 questions