Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Vce PMI-100 Questions Latest

Page: 4 / 26
Total 704 questions

Certified Associate in Project Management (CAPM)® Questions and Answers

Question 13

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Question 14

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Question 15

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Question 16

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Page: 4 / 26
Total 704 questions