Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Free PMI-100 Questions Attempt

Page: 18 / 26
Total 704 questions

Certified Associate in Project Management (CAPM)® Questions and Answers

Question 69

Which input will be used when tasked with developing the human resource plan?

Options:

A.

Project management plan

B.

Activity resource requirements

C.

Resource calendar

D.

Project staff assignments

Question 70

Which of the following is an input to the Develop Project Charter process?

Options:

A.

Work performance information

B.

Project management plan

C.

Business case

D.

Change requests

Question 71

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

Options:

A.

Cost Plus Award Fee Contract (CPAF)

B.

Firm-Fixed -Price Contract (FFP)

C.

Time and Material Contract (T&M)

D.

Cost Plus Incentive Fee Contract (CPIF)

Question 72

The correct equation for schedule variance (SV) is earned value:

Options:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Page: 18 / 26
Total 704 questions