Certified Associate in Project Management (CAPM)® Questions and Answers

Question 101

The scope management plan is a subsidiary of which project document?

Options:

A.

Schedule management plan

B.

Project management plan

C.

Quality management plan

D.

Resource management plan

Question 102

The Define Scope process is in which of the following Process Groups?

Options:

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Question 103

Which of the following is a narrative description of products, services, or results to be delivered by a project?

Options:

A.

Project statement of work

B.

Business case

C.

Accepted deliverable

D.

Work performance information

Question 104

As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?

Options:

A.

BAC

B.

EAC

C.

ETC

D.

WBS