Question 29

The progressive detailing of the project management plan is called:

Options:

A.

expert judgment.

B.

rolling wave planning.

C.

work performance information.

D.

specification.

Question 30

Project contracts generally fall into which of the following three broad categories?

Options:

A.

Fixed-price, cost reimbursable, time and materials

B.

Make-or-buy, margin analysis, fixed-price

C.

Time and materials, fixed-price, margin analysis

D.

Make-or-buy, lump-sum, cost-plus-incentive

Question 31

Which of the following is an input to the Perform Qualitative Risk Analysis process?

Options:

A.

Risk register

B.

Risk data quality assessment

C.

Risk categorization

D.

Risk urgency

Question 32

Which tool and technique is used in Conduct Procurements?

Options:

A.

Teaming agreements

B.

Expert judgment

C.

Bidder conferences

D.

Contract types

Page: 8 / 26
Total 704 questions