Summer Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI-SP Exam Dumps : PMI Scheduling Professional

PDF
PMI-SP pdf
 Real Exam Questions and Answer
 Last Update: Oct 10, 2025
 Question and Answers: 323
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$29.75  $84.99
PMI-SP exam
PDF + Testing Engine
PMI-SP PDF + engine
 Both PDF & Practice Software
 Last Update: Oct 10, 2025
 Question and Answers: 323
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$47.25  $134.99
Testing Engine
PMI-SP Engine
 Desktop Based Application
 Last Update: Oct 10, 2025
 Question and Answers: 323
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$35  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

PMI Scheduling Professional Questions and Answers

Question 1

You are the project manager for the GHB Organization. Management has asked that you review your recent SPI to determine why there was a schedule variance. They'd also like you to explain what approach you'll do to counteract the SPI going forward in the project. You complete the variance analysis and report to management that you'll be fast tracking a portion of your project work. What will be the management's concern with, when it comes to fast tracking the project?

Options:

A.

Added costs for the additional project labor

B.

Added risk

C.

Continued variances in the SPI

D.

Slippage in the project quality

Buy Now
Question 2

Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

Options:

A.

Resource competition

B.

Matrix organization

C.

Resource requirement

D.

Resource constraint

Question 3

Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the project completion date, so Gina is stressing to her project team members that while they need to provide and account for all of the project activities, they should focus on one work package in the WBS at a time. In order to start the decomposition of the project work packages into activities, Gina will need all of the following except for which one?

Options:

A.

Scope baseline

B.

Organizational process assets

C.

WBS

D.

Enterprise environmental factors