CIMA Related Exams
E2 Exam
A building project for developing new homes to customers' own specification is behind schedule and will incur penalty payments if the next milestone is not achieved on time.
Which of the following strategies would be appropriate in order to get the project back on track and that will not compromise customer satisfaction and could still minimse the overall cost of development?
Select All that apply.
A project manager is calculating the budget cost of a single project task called "Server Configuration".
This task is estimated to last 8 weeks and requires the full-time services of two software consultants, both for the entire duration of the task.
One consultant commands an inclusive rate of $400/day and the other $40/hour based on an eight hour day. Fixed hardware costs of $12,000 have also been estimated for the task.
Calculate the total budget cost for the task (ignoring any other resources or costs) - assuming a five day working week.
Give your answer as a whole number.
The total cost is $ .
GG, the new CEO in an organisation, was surprised to find out that the company does not undertake competitor analysis. He was told that, as the organisation operates in a very dynamic market, things change too quickly to make analysis worthwhile.
Choose from the following the option that presents why competitor analysis is important.