New Year Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Free and Premium CIPS L4M3 Dumps Questions Answers

Page: 1 / 17
Total 233 questions

Commercial Contracting Questions and Answers

Question 1

John is a new procurement manager who has recently joined Smiths Facilities Management Ltd. The company provides maintenance services through the utilisation of subcontractors. It is experiencing a number of issues with its supply chain which has resulted in customer complaints, and John would like to introduce service level agreements (SLAs) to some of its key providers. Which of the following should be included?

    How often the service will be provided

    The procedures to be followed to resolve disputes

    The qualifications needed by staff providing the service

    The stock maintained by the subcontractor

Options:

A.

1, 3 and 4 only

B.

2, 3 and 4 only

C.

1, 2 and 4 only

D.

1, 2 and 3 only

Buy Now
Question 2

Which of the following is likely to reduce risks of different rules regarding when offers and acceptance become effective between legal systems?

Options:

A.

Withdrawal protocol

B.

Letter of intent

C.

Time lapse

D.

Deemed receipt protocol

Question 3

Which of the following will be always automatically deemed as a consideration?

Options:

A.

Promise to perform over and above an existing obligation

B.

Promise given to a third party

C.

Implied consideration

D.

Past consideration

Question 4

CMS Corp goes into a gainshare agreement with the contractor, EIP Ltd. Both parties agree that the final fee will be calculated on target cost - target fee basis. Which of the following will affect the final fee payable in this gainshare agreement? Select TWO that apply:

Options:

A.

Accrual expense

B.

Final price

C.

Purchaser goodwill

D.

Supplier share

E.

Actual cost

Question 5

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

Options:

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Question 6

In a contract, express terms and implied terms may contradict on the same issues. Under which of the following circumstances, implied terms will override express terms?

Options:

A.

Implied terms are created by trade customs

B.

Contracting parties are silent on a matter that was not included in express terms

C.

No circumstances. Express terms always take precedence over implied terms

D.

Implied terms are created by law which prevents them to be overridden

Question 7

What is an example of the legal term an 'Invitation to treat'?

Options:

A.

A response to a quotation from a supplier

B.

An invitation to another person to make an offer to contract

C.

An invitation to work in partnership with another supplier

D.

A formal agreed contract between two or more parties

Question 8

According to mailbox rule in some common law countries, at which point the offeree's acceptance will be effective?

Options:

A.

When the letter of acceptance is opened and its contents read by the offeree.

B.

When the letter of acceptance is received by the offeror.

C.

When the letter of acceptance has been written.

D.

When the letter of acceptance has been correctly addressed, its postage paid, and posted.

Question 9

A construction company wishes to place the contract for the building of a new hotel to a principal contractor using a model form contract. Which of these is an advantage of using a 'model form contract?'

Options:

A.

Incentive payment terms can be included to reward the supplier for attainment of cost savings

B.

Formulae or indices can be included to assess any additional supplier's claims for contract price adjustment

C.

It avoids the requirement to create complex contracts each time but can be adapted to suit particular circumstances

D.

Legal advice is still required if significant amendments or variations are to be made to the contract

Question 10

Maximum Score: 1

When a company has decided to outsource part of its operation, the contract will need to include a number of key contract terms to minimise risk. Which of the following should be included?

    A confidentiality clause designed to protect either party

    A clause stating how long the service is to be outsourced

    A clause stating how long the employees can take for holiday

    A contract variation and price adjustment clause

Options:

A.

1 and 4 only

B.

1 and 2 only

C.

3 and 4 only

D.

2 and 4 only

Question 11

Royal Naval Hospital at Rockstown, Anyport manages a fleet of nine ambulance vehicles. During busy periods, it becomes very difficult to keep track of the location of each ambulance (and the nature of their journey). Continual problems lead to the proposal for a new control system (ERNS).

For this ERNS project, the procurement department has drafted a specification in which only a bullet point list of basic requirements was written down. The procurement manager understands that the specification should be developed more specifically but a cross functional team from the Hospital could not do that. A senior buyer suggests that some of Hospital's pre-qualified suppliers could support them in developing the specification.

Which of the following should be a priority approach of procurement department in developing dialogue with those suppliers about specification development?

Options:

A.

Internal discussion

B.

General networking

C.

One-to-one meeting with the suppliers

D.

Request for quotation from the suppliers

Question 12

Maximum Score 1

Buyer O has placed an order for the supply and installation of six new servers for a total amount of £600,000 from Supplier A. Which of the following could potentially be treated as examples of a liquidated damages clause within the contract for the supply of the servers?

    If the supplier delivers any of the servers late, £1,000 per server will be deducted from the order per day

    This contract is subject to delay remedies of £X - the amount to be agreed by both parties during delivery

    The sum for breach of the completion date for the order is £40,000 per day up to a maximum of 50% of the contract price

    If the performance of any of the servers degrades within five years, a full refund of £600,000 will be provided

Options:

A.

1 and 2 only

B.

3 and 4 only

C.

1 and 3 only

D.

2 and 4 only

Question 13

Which of the following is the contract provision that relieves the parties from performing their contractual obligations when certain circumstances like natural disasters, terrorist attacks, etc arise?

Options:

A.

Indemnity clause

B.

Liquidated damage clause

C.

Insurance clause

D.

Exclusion clause

Question 14

Which of the following shall help the purchaser control the selection of tier 2 suppliers?

Options:

A.

Subcontracting clause

B.

Warranty clause

C.

Guarantee clause

D.

Insurance clause

Question 15

In which of the following conditions, request for quotation produces the best results?

Options:

A.

With an ambiguous specification

B.

Under framework agreements

C.

Under a complex process

D.

With strategic items

Question 16

Danielle buys a car from Aaron. Not long after, she receives an proposal from Brian, who isinterested in buying the car but his budget is very constraint. Then, Brian decides to sign a hire purchase agreement with Danielle which lasts 4 years. Brian lives very far from Danielle, so hehires Charlie to deliver the car to his place. During the transport, Charlie has an accident and the car is written off. At the time of accident, who has the title of the car?

Options:

A.

Charlie

B.

Aaron

C.

Brian

D.

Danielle

Question 17

ABC Ltd is a UK based company. It plans to enter into a contract with XYZ Ltd which is based in Singapore. Which of the following are the mandatory elements for the contract between ABC Ltd and XYZ Ltd to be legally binding? Select THREE that apply.

Options:

A.

All parties must have capacity to contract

B.

The two parties must have intention to be bound

C.

The invitation to tender must be sent by the agreed deadline

D.

There must be an offer and an acceptance

E.

An amount of money must be paid upfront

F.

There must be an invitation to treat

Question 18

Curnoe Ltd supplied tyres to Garage Ltd. Garage Ltd agreed in the contract that for any specified breaches of contract, it would pay Curnoe Ltd £5 per tyre sold in breach. It subsequently sold tyres at below the listed price, which was one of the breaches mentioned in the contract. What is the £5 per tyre provision an example of?

Options:

A.

Quantum meruit

B.

Exclusion clause

C.

Liquidated damages

D.

Unliquidated damages

Question 19

Which of the following is an example of liquidated damages clause?

1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."

2. “If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"

3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."

4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"

Options:

A.

2 and 4 only

B.

1 and 3 only

C.

3 and 4 only

D.

1 and 2 only

Question 20

Which of the following are the 'fundamental' labour standards laid down by the International Labour Organisation?

1. Elimination of child labour

2. Payment of a minimum wage

3. The right to collective bargaining

4. Abolition of forced labor

Options:

A.

1, 2 and 4 only

B.

2, 3 and 4 only

C.

1, 3 and 4 only

D.

1, 2 and 3 only

Question 21

Which of the following approaches could a purchasing organisation use to reduce the level of detail in a specification, without increasing the risk of an unsuccessful procurement process?

Increase the use of acronyms and abbreviations

Cross-refer to recognised industry standards

Require tendering suppliers to propose specifications

Provide samples to demonstrate the requirements

Options:

A.

1 and 3 only

B.

2 and 4 only

C.

2 and 3 only

D.

1 and 4 only

Question 22

What pricing arrangements or schedule would be used if the buyer is operating to an exact budget?

Options:

A.

Cost-plus pricing arrangement

B.

Fixed pricing arrangement

C.

Incentivised pricing arrangement

D.

Indexation pricing arrangement

Question 23

Maximum Score: 1

Which of the following would be considered as advantages of an industry model form contract?

    It provides greater flexibility for negotiation

    It reduces the cost of contract development

    It is usually designed to be fair to both parties

    It removes the need for the buyer to understand it

Options:

A.

1 and 2 only

B.

2 and 3 only

C.

1 and 3 only

D.

2 and 4 only

Question 24

Maximum Score: 1

Setting key performance indicators (KPIs) for supplier performance should ensure ...

Options:

A.

reduced vendor base

B.

managed supply risks

C.

lowest price for products

D.

earliest delivery

Question 25

Which of the following would be considered as advantages of an industry model form contract?

It provides greater flexibility for negotiation

It reduces the cost of contract development

It is usually designed to be fair to both parties

It removes the need for the buyer to understand it

Options:

A.

1 and 2 only

B.

2 and 4 only

C.

1 and 3 only

D.

2 and 3 only

Question 26

Which of the following are most likely to be substantive elements of the specification of a truck? Select TWO that apply:

Options:

A.

Guarantee

B.

Foreword

C.

Expected lifespan

D.

Ethics

E.

Abbreviation

Question 27

Maximum Score 1

When a company has decided to outsource part of its operation, the contract will need to include a number of key contract terms to minimise risk. Which of the following should be included?

    A confidentiality clause designed to protect either party

    A clause stating how long the service is to be outsourced

    A clause stating how long the employees can take for holiday

    A contract variation and price adjustment clause

Options:

A.

1 and 4 only

B.

1 and 2 only

C.

3 and 4 only

D.

2 and 4 only

Question 28

According to rule of contract formation, which of the following is a valid acceptance?

Options:

A.

The person orally agrees to pay the offered price

B.

The person states that she is able to pay the offered price

C.

The person asks for a lower price

D.

The person says that she will think about it overnight

Question 29

In which scenarios would it be appropriate for a procurement organisation to include contractual indexation and/or price adjustment formulae clauses in a services contract? Select TWO that apply.

Options:

A.

The supplier’s directors shall be paid dividends during the term

B.

The supplier’s contract staffing costs will be subject to regulatory increase

C.

The material components were tendered as fixed costs for the term

D.

The supplier’s preference is to switch to a more expensive material specification

E.

The market rates for the supplier's material costs will vary during the term

Question 30

A senior procurement specialist in UK is preparing a specification in which ISO standards are used to send to global suppliers. Is this action appropriate?

Options:

A.

No, the procurement specialist must use BSI standards instead

B.

Yes, evert specification must have ISO standards

C.

Yes, ISO standards are globally recognisable

D.

No, ISO standards are unfamiliar to global suppliers

Question 31

Which of the following are likely to be implied terms in a contract? Select TWO that apply:

Options:

A.

Legal precedence

B.

Definition & interpretation

C.

Contract appendix

D.

Statute

E.

Contract clause

Question 32

Which of the following will be included in a conformance specification?

1. Brand names

2. Description of the operating environments

3. Chemical formulae

4. Required safety level

Options:

A.

1 and 2 only

B.

1 and 3 only

C.

1 and 4 only

D.

2 and 3 only

Question 33

The contracts manager at a newly established private transport agency, Travel Response Services (TRS), has been asked to draft a set of standard terms and conditions that will protect customers’ personal information when it is passed to sub-contracted suppliers by TRS. Which standard clause would be best suited for this?

Options:

A.

An intellectual property rights clause

B.

An invoicing and payment clause

C.

A corporate social responsibility clause

D.

A confidentiality and use of data clause

Question 34

Which of the following can be considered as implied terms in a contract?

1. Case law

2. Statute

3. Trade custom

4. A term can never be implied, it must always be expressed by the parties

Options:

A.

1,3 and 4 only

B.

1, 2 and 3 only

C.

1, 2 and 4 only

D.

2, 3 and 4 only

Question 35

Misrepresentation can be defined as a false statement of material fact made by one of the contracting parties which was intended to (and did) induce the other party to make the contract. What remedies are available in this instance to the innocent party?

Options:

A.

Contract is voidable and damages can be claimed

B.

Contract is not voidable but damages can still be claimed

C.

Contract is voidable and must be amended and performed

D.

Contract is not voidable and it is too late to take any action

Question 36

When a supplier signs an insurance policy with an insurance company, which of the following is transferred to insurance company?

Options:

A.

Right

B.

Risk

C.

Legal responsibility

D.

Contractual obligation

Question 37

Which of the following are likely to be advantages of using request for quotation? Select TWO that apply:

Options:

A.

Lower administration costs

B.

Short turnaround times

C.

No specification required

D.

Helping the buying organisation assess both price and quality

E.

Encouraging suppliers to submit creative solutions

Question 38

Which of the following regulates barriers to the trade of goods between Member States of WTO?

Options:

A.

NAFTA

B.

GATT

C.

CISG

D.

TRIPS

Question 39

Maximum Score 1

A construction company wishes to place the contract for the building of a new hotel to a principal contractor using a model form contract. Which of these is an advantage of using a ‘model form contract’?

Options:

A.

It avoids the requirement to create complex contracts each time but can be adapted to suit particular circumstances

B.

Formulae or indices can be included to assess any additional supplier’s claims for contract price adjustment

C.

Incentive payment terms can be included to reward the supplier for attainment of cost savings

D.

Legal advice is still required if significant amendments or variations are to be made to the contract

Question 40

Which of the following will always give rise to a claim of misrepresentation?

1. Silence

2. False thought

3. Statement of fact

4. Representation by conduct

Options:

A.

1 and 2 only

B.

1 and 3 only

C.

3 and 4 only

D.

2 and 4 only

Question 41

As a result of a global pandemic, a local hospital is facing significant patient capacity pressures and would like the construction of a new 50-bed ward to be prioritised and fully operational at the earliest opportunity. Which of the following pricing arrangements would support this aspiration?

Options:

A.

Incentivised contract pricing

B.

Fixed price economic adjustment pricing

C.

Time and materials arrangement pricing

D.

Penetration contract pricing

Question 42

Under which of the following scenarios an RFQ is most likely to be used?

Options:

A.

Purchase of a small number of standardised products under a framework agreement

B.

Purchase of complex machinery

C.

Design of a unique and complex software code

D.

When the buying organisation does not know the requirements in details and needs the input from suppliers

Question 43

Which of the following is a disadvantage of using input specifications?

Options:

A.

It is difficult to assess suitability of each quotation

B.

It requires a more proactive approach to monitoring

C.

There is less opportunity for innovation

D.

There is no limit to the number of suppliers who can quote

Question 44

If a false statement of material fact is made by one of the contracting parties, the misled party will have remedies for:

Options:

A.

Indemnity

B.

Misrepresentation

C.

Recission

D.

Damages

Question 45

Which of the following are examples of conformance specification? Select TWO that apply:

Options:

A.

Outcome-focused specification

B.

Statement of work

C.

Product sample

D.

Output-focused specification

E.

Technical drawing

Question 46

Adornical Toys Ltd have recently declared their commitment to international labour standards. Karim is sourcing a supplier for a new range of wooden toys and is keen to ensure that the organisation's corporate objectives are met. Which of the following approaches could he include as part of his specification requirements to achieve this labour outcome?

Options:

A.

Certification to an ethical trading initiative

B.

Formally measure their carbon footprint

C.

Use ecologically certified raw materials

D.

Accreditation to waste reduction schemes

Question 47

Which of these describes “consideration” within a contract?

Options:

A.

The communication of an unconditional agreement

B.

Both parties exchange something of value

C.

The desire of both parties to enter into a contract

D.

Ability of both parties to be able to enter into a contract

Question 48

A buyer is procuring innovative new IT systems and has issued a performance specification as part of the invitation to tender. Is this a suitable approach?

Options:

A.

No, because the bidder may use it to inflate costs

B.

Yes, because it allows the bidder to present solutions and further inform the requirement

C.

No, because the Procurement Team should only include outputs in specifications

D.

Yes, because it will improve relationships and collaboration between both parties

Question 49

Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.

Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.

Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.

Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?

Options:

A.

Yes, because Cleveland needs to seek rescission first before claiming for damages

B.

Yes, because both parties agreed with rescission of their contract

C.

No, because the work had been carried out which could not be returned

D.

No, because the contract does not include any provision on rescission

Question 50

Prior to circulating the service specification to a tendering supplier, it is good practice for the purchasing organisation to request completion of a non-disclosure agreement. Is this statement correct?

Options:

A.

No, because the non-disclosure agreement has no legal standing

B.

Yes, because the non-disclosure agreement protects intellectual property

C.

Yes, because the non-disclosure agreement encourages transparent bidding

D.

No, because the non-disclosure agreement only applies after contracting

Question 51

Which of the following is always an advantage of using fixed price arrangement in a contract for buying organisation?

Options:

A.

Buyer can allocate budget with certainty

B.

Buyer can harness falling market price

C.

Supplier always receives a fixed margin

D.

Suitable for contracts that last 5 years or more

Question 52

Under hire purchase agreement, when will the ownership of asset legally belong to the purchaser?

Options:

A.

When the final instalment is paid

B.

When the purchaser takes possession of the asset

C.

When the down payment is made

D.

When the agreement is signed

Question 53

Maximum Score: 1

An urgent component requirement needs to be purchased to meet the timescales of a project. A supplier proposes using its standard terms and conditions. What risk to the buying organisation could this bring?

Options:

A.

A breach of competition laws

B.

Contract conditions that are favourable to the buyer

C.

A breach of the supplier's internal financial controls

D.

Contract conditions that are favourable to the supplier

Question 54

In the UK, Unfair Contract Terms Act 1977 regulates which of the following?

Options:

A.

Validity of a contract when it is formed on the basis of misrepresentation

B.

Rules regarding battle of the forms

C.

Effectiveness of contract terms in the standard terms and conditions

D.

Rule of offer and acceptance

Question 55

Solus Trading has begun a project to improve the level of delivery performance from its suppliers. They need to develop a key performance indicator (KPI) to measure the performance improvement. Which KPI would be suitable to use?

Options:

A.

Percentage of on-time in full

B.

Percentage of rejects and returns

C.

Percentage of cost reduction

D.

Percentage of customer complaints

Question 56

Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.

Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.

Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.

Hank’s pre-contractual assurance is most likely to be an example of which of the following?

Options:

A.

Inaccuracy in communication

B.

Threat

C.

Initial impossibility

D.

Fraudulent misrepresentation

Question 57

Which of the following is the reason why liquidated damage clauses are embedded into a contract?

Options:

A.

Because liquidated damages are the only remedy

B.

To penalise the supplier for their wrongdoing

C.

To avoid argument on correct measure of damage

D.

Because compensation will be awarded immediately

Question 58

Maximum Score 6

An urgent component requirement needs to be purchased to meet the timescales of a project. A supplier proposes using its standard terms and conditions. What risk to the buying organisation could this bring?

Options:

A.

A breach of competition laws

B.

Contract conditions that are favourable to the buyer

C.

A breach of the supplier’s internal financial controls

D.

Contract conditions that are favourable to the supplier

Question 59

Which of the following is a true statement on express and implied terms?

Options:

A.

Express terms always take precedent over implied terms

B.

Implied terms may derive from oral negotiations

C.

Express terms must always be in writing

D.

Express terms must be prepared by the party with expert knowledge

Question 60

Maximum Score 1

Which of the following would you expect to see in an Invitation to Tender (ITT)?

Options:

A.

Best and Final Offer (BAFO)

B.

Supplier rates

C.

Liquidity ratios

D.

Delivery milestones

Question 61

The model form contract invented by Institute of Civil Engineers is...?

Options:

A.

NEC

B.

IMechE/IET

C.

FIDIC

D.

JCT

Question 62

Which of the following statements is FALSE on contracts for the leasing of assets?

Options:

A.

The party responsible for maintenance, insurance and taxes is subject to negotiation

B.

In lease agreement, the possession and right of use of an asset are transferred to the lessee

C.

The ownership of leased asset is transferred to the lessee at the end of the period

D.

The lessee may bear some risks of ownership, such as the liability to insure the asset

Question 63

The nature of the "Battle of the forms" is when both buyer and supplier are attempting to ...

Options:

A.

secure their own terms and conditions

B.

create a collaborative relationship

C.

create a performance specification

D.

form a joint contract

Question 64

Which of the following may be a benefit for purchaser in using call off contract?

Options:

A.

Ability to discover new potential suppliers

B.

No long-term commitment required

C.

Secured supply

D.

Maintaining a degree of competition between suppliers

Question 65

Consequences and actions that arise from certain KPI scores must be...? Select TWO that apply.

Options:

A.

Mutually agreed

B.

Deliberately omitted

C.

Documented

D.

Unilaterally imposed by the purchaser

E.

Terminated

Question 66

Which of the following are the conditions for revocation of offer to be valid?

1. The offeree has not received the offer yet

2. Revocation of offer must be communicated with the offeree

3. Revocation of offer must be sent via email

4. Offeree has not accepted the offer yet

Options:

A.

2 and 4 only

B.

1 and 4 only

C.

1 and 3 only

D.

2 and 3 only

Question 67

Which of the following sections would typically be included in a specification for services? Select THREE that apply.

Options:

A.

A description of the service requirements

B.

The tender evaluation methodology

C.

The fault rectification timeframes

D.

The service start and end dates

E.

The terms and conditions of the contract

F.

Questions relating to methods

Question 68

The cost in cost reimbursable contract is...?

Options:

A.

Actual cost

B.

Variable cost

C.

Fixed cost

D.

Profit

Question 69

In order to reduce the internal cost of administration from the raising of high-volume, low-value orders such as office stationery, a procurement manager implements the use of call-off orders for such circumstances. Is this an acceptable thing to do?

Options:

A.

No, the procurement manager fears that they will lose staff and prefers to keep the administration costs high

B.

No, as the role of the administration staff is to keep a check on the items being ordered and they would lose this ability

C.

Yes, as the procurement manager will be able to track more easily the volume of small orders and where the spend is occurring

D.

Yes, the use of a blanket order cuts the staff administration time and paperwork that would be involved in numerous small orders

Page: 1 / 17
Total 233 questions