John is a new procurement manager who has recently joined Smiths Facilities Management Ltd. The company provides maintenance services through the utilisation of subcontractors. It is experiencing a number of issues with its supply chain which has resulted in customer complaints, and John would like to introduce service level agreements (SLAs) to some of its key providers. Which of the following should be included?
How often the service will be provided
The procedures to be followed to resolve disputes
The qualifications needed by staff providing the service
The stock maintained by the subcontractor
Which of the following is likely to reduce risks of different rules regarding when offers and acceptance become effective between legal systems?
Which of the following will be always automatically deemed as a consideration?
CMS Corp goes into a gainshare agreement with the contractor, EIP Ltd. Both parties agree that the final fee will be calculated on target cost - target fee basis. Which of the following will affect the final fee payable in this gainshare agreement? Select TWO that apply:
GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.
Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.
Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?
In a contract, express terms and implied terms may contradict on the same issues. Under which of the following circumstances, implied terms will override express terms?
What is an example of the legal term an 'Invitation to treat'?
According to mailbox rule in some common law countries, at which point the offeree's acceptance will be effective?
A construction company wishes to place the contract for the building of a new hotel to a principal contractor using a model form contract. Which of these is an advantage of using a 'model form contract?'
Maximum Score: 1
When a company has decided to outsource part of its operation, the contract will need to include a number of key contract terms to minimise risk. Which of the following should be included?
A confidentiality clause designed to protect either party
A clause stating how long the service is to be outsourced
A clause stating how long the employees can take for holiday
A contract variation and price adjustment clause
Royal Naval Hospital at Rockstown, Anyport manages a fleet of nine ambulance vehicles. During busy periods, it becomes very difficult to keep track of the location of each ambulance (and the nature of their journey). Continual problems lead to the proposal for a new control system (ERNS).
For this ERNS project, the procurement department has drafted a specification in which only a bullet point list of basic requirements was written down. The procurement manager understands that the specification should be developed more specifically but a cross functional team from the Hospital could not do that. A senior buyer suggests that some of Hospital's pre-qualified suppliers could support them in developing the specification.
Which of the following should be a priority approach of procurement department in developing dialogue with those suppliers about specification development?
Maximum Score 1
Buyer O has placed an order for the supply and installation of six new servers for a total amount of £600,000 from Supplier A. Which of the following could potentially be treated as examples of a liquidated damages clause within the contract for the supply of the servers?
If the supplier delivers any of the servers late, £1,000 per server will be deducted from the order per day
This contract is subject to delay remedies of £X - the amount to be agreed by both parties during delivery
The sum for breach of the completion date for the order is £40,000 per day up to a maximum of 50% of the contract price
If the performance of any of the servers degrades within five years, a full refund of £600,000 will be provided
Which of the following is the contract provision that relieves the parties from performing their contractual obligations when certain circumstances like natural disasters, terrorist attacks, etc arise?
Which of the following shall help the purchaser control the selection of tier 2 suppliers?
In which of the following conditions, request for quotation produces the best results?
Danielle buys a car from Aaron. Not long after, she receives an proposal from Brian, who isinterested in buying the car but his budget is very constraint. Then, Brian decides to sign a hire purchase agreement with Danielle which lasts 4 years. Brian lives very far from Danielle, so hehires Charlie to deliver the car to his place. During the transport, Charlie has an accident and the car is written off. At the time of accident, who has the title of the car?
ABC Ltd is a UK based company. It plans to enter into a contract with XYZ Ltd which is based in Singapore. Which of the following are the mandatory elements for the contract between ABC Ltd and XYZ Ltd to be legally binding? Select THREE that apply.
Curnoe Ltd supplied tyres to Garage Ltd. Garage Ltd agreed in the contract that for any specified breaches of contract, it would pay Curnoe Ltd £5 per tyre sold in breach. It subsequently sold tyres at below the listed price, which was one of the breaches mentioned in the contract. What is the £5 per tyre provision an example of?
Which of the following is an example of liquidated damages clause?
1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."
2. “If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"
3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."
4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"
Which of the following are the 'fundamental' labour standards laid down by the International Labour Organisation?
1. Elimination of child labour
2. Payment of a minimum wage
3. The right to collective bargaining
4. Abolition of forced labor
Which of the following approaches could a purchasing organisation use to reduce the level of detail in a specification, without increasing the risk of an unsuccessful procurement process?
Increase the use of acronyms and abbreviations
Cross-refer to recognised industry standards
Require tendering suppliers to propose specifications
Provide samples to demonstrate the requirements
What pricing arrangements or schedule would be used if the buyer is operating to an exact budget?
Maximum Score: 1
Which of the following would be considered as advantages of an industry model form contract?
It provides greater flexibility for negotiation
It reduces the cost of contract development
It is usually designed to be fair to both parties
It removes the need for the buyer to understand it
Maximum Score: 1
Setting key performance indicators (KPIs) for supplier performance should ensure ...
Which of the following would be considered as advantages of an industry model form contract?
It provides greater flexibility for negotiation
It reduces the cost of contract development
It is usually designed to be fair to both parties
It removes the need for the buyer to understand it
Which of the following are most likely to be substantive elements of the specification of a truck? Select TWO that apply:
Maximum Score 1
When a company has decided to outsource part of its operation, the contract will need to include a number of key contract terms to minimise risk. Which of the following should be included?
A confidentiality clause designed to protect either party
A clause stating how long the service is to be outsourced
A clause stating how long the employees can take for holiday
A contract variation and price adjustment clause
According to rule of contract formation, which of the following is a valid acceptance?
In which scenarios would it be appropriate for a procurement organisation to include contractual indexation and/or price adjustment formulae clauses in a services contract? Select TWO that apply.
A senior procurement specialist in UK is preparing a specification in which ISO standards are used to send to global suppliers. Is this action appropriate?
Which of the following are likely to be implied terms in a contract? Select TWO that apply:
Which of the following will be included in a conformance specification?
1. Brand names
2. Description of the operating environments
3. Chemical formulae
4. Required safety level
The contracts manager at a newly established private transport agency, Travel Response Services (TRS), has been asked to draft a set of standard terms and conditions that will protect customers’ personal information when it is passed to sub-contracted suppliers by TRS. Which standard clause would be best suited for this?
Which of the following can be considered as implied terms in a contract?
1. Case law
2. Statute
3. Trade custom
4. A term can never be implied, it must always be expressed by the parties
Misrepresentation can be defined as a false statement of material fact made by one of the contracting parties which was intended to (and did) induce the other party to make the contract. What remedies are available in this instance to the innocent party?
When a supplier signs an insurance policy with an insurance company, which of the following is transferred to insurance company?
Which of the following are likely to be advantages of using request for quotation? Select TWO that apply:
Which of the following regulates barriers to the trade of goods between Member States of WTO?
Maximum Score 1
A construction company wishes to place the contract for the building of a new hotel to a principal contractor using a model form contract. Which of these is an advantage of using a ‘model form contract’?
Which of the following will always give rise to a claim of misrepresentation?
1. Silence
2. False thought
3. Statement of fact
4. Representation by conduct
As a result of a global pandemic, a local hospital is facing significant patient capacity pressures and would like the construction of a new 50-bed ward to be prioritised and fully operational at the earliest opportunity. Which of the following pricing arrangements would support this aspiration?
Under which of the following scenarios an RFQ is most likely to be used?
Which of the following is a disadvantage of using input specifications?
If a false statement of material fact is made by one of the contracting parties, the misled party will have remedies for:
Which of the following are examples of conformance specification? Select TWO that apply:
Adornical Toys Ltd have recently declared their commitment to international labour standards. Karim is sourcing a supplier for a new range of wooden toys and is keen to ensure that the organisation's corporate objectives are met. Which of the following approaches could he include as part of his specification requirements to achieve this labour outcome?
Which of these describes “consideration” within a contract?
A buyer is procuring innovative new IT systems and has issued a performance specification as part of the invitation to tender. Is this a suitable approach?
Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?
Prior to circulating the service specification to a tendering supplier, it is good practice for the purchasing organisation to request completion of a non-disclosure agreement. Is this statement correct?
Which of the following is always an advantage of using fixed price arrangement in a contract for buying organisation?
Under hire purchase agreement, when will the ownership of asset legally belong to the purchaser?
Maximum Score: 1
An urgent component requirement needs to be purchased to meet the timescales of a project. A supplier proposes using its standard terms and conditions. What risk to the buying organisation could this bring?
In the UK, Unfair Contract Terms Act 1977 regulates which of the following?
Solus Trading has begun a project to improve the level of delivery performance from its suppliers. They need to develop a key performance indicator (KPI) to measure the performance improvement. Which KPI would be suitable to use?
Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Hank’s pre-contractual assurance is most likely to be an example of which of the following?
Which of the following is the reason why liquidated damage clauses are embedded into a contract?
Maximum Score 6
An urgent component requirement needs to be purchased to meet the timescales of a project. A supplier proposes using its standard terms and conditions. What risk to the buying organisation could this bring?
Which of the following is a true statement on express and implied terms?
Maximum Score 1
Which of the following would you expect to see in an Invitation to Tender (ITT)?
The model form contract invented by Institute of Civil Engineers is...?
Which of the following statements is FALSE on contracts for the leasing of assets?
The nature of the "Battle of the forms" is when both buyer and supplier are attempting to ...
Which of the following may be a benefit for purchaser in using call off contract?
Consequences and actions that arise from certain KPI scores must be...? Select TWO that apply.
Which of the following are the conditions for revocation of offer to be valid?
1. The offeree has not received the offer yet
2. Revocation of offer must be communicated with the offeree
3. Revocation of offer must be sent via email
4. Offeree has not accepted the offer yet
Which of the following sections would typically be included in a specification for services? Select THREE that apply.
The cost in cost reimbursable contract is...?
In order to reduce the internal cost of administration from the raising of high-volume, low-value orders such as office stationery, a procurement manager implements the use of call-off orders for such circumstances. Is this an acceptable thing to do?