Commercial Contracting Questions and Answers

Question 41

As a result of a global pandemic, a local hospital is facing significant patient capacity pressures and would like the construction of a new 50-bed ward to be prioritised and fully operational at the earliest opportunity. Which of the following pricing arrangements would support this aspiration?

Options:

A.

Incentivised contract pricing

B.

Fixed price economic adjustment pricing

C.

Time and materials arrangement pricing

D.

Penetration contract pricing

Question 42

Under which of the following scenarios an RFQ is most likely to be used?

Options:

A.

Purchase of a small number of standardised products under a framework agreement

B.

Purchase of complex machinery

C.

Design of a unique and complex software code

D.

When the buying organisation does not know the requirements in details and needs the input from suppliers

Question 43

Which of the following is a disadvantage of using input specifications?

Options:

A.

It is difficult to assess suitability of each quotation

B.

It requires a more proactive approach to monitoring

C.

There is less opportunity for innovation

D.

There is no limit to the number of suppliers who can quote

Question 44

If a false statement of material fact is made by one of the contracting parties, the misled party will have remedies for:

Options:

A.

Indemnity

B.

Misrepresentation

C.

Recission

D.

Damages