Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

L4M3 Exam Dumps : Commercial Contracting

PDF
L4M3 pdf
 Real Exam Questions and Answer
 Last Update: May 10, 2026
 Question and Answers: 233 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
L4M3 exam
PDF + Testing Engine
L4M3 PDF + engine
 Both PDF & Practice Software
 Last Update: May 10, 2026
 Question and Answers: 233
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
L4M3 Engine
 Desktop Based Application
 Last Update: May 10, 2026
 Question and Answers: 233
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Commercial Contracting Questions and Answers

Question 1

GPP, the employer, and Prosolia UK, the contractor, entered into five EPC contracts for the development of five different solar power generation plants in the United Kingdom. Four out of the five developments failed to be commissioned by the relevant due dates, with the delays ranging from 44 to 285 days.

Among other claims, GPP, acting through its two investment vehicles, claimed liquidated damages of £500 per day in all four contracts for Prosolia UK's failure to achieve completion of the plants by the due date. The liquidated damages claimed amounted to £1,804,221 across the four delayed contracts.

Prosolia, alongside various other defences, raised the defence that the liquidated damages provision in each contract was a penalty, and therefore unenforceable against it. Is Prosolia contractually obliged to make the payment to the plaintiff?

Options:

A.

No, the amount claimed is too excessive and it may put Prosolia into insolvency. The clause must be void

B.

No, the clause must be treated as a penalty clause which is unenforceable in UK

C.

Yes, the amount is a reward to the employer as they have supervised and monitored the projects

D.

Yes, the clause is a genuine estimate of possible losses that GPP may have suffered and therefore, it is enforceable.

Buy Now
Question 2

Solus Trading has begun a project to improve the level of delivery performance from its suppliers. They need to develop a key performance indicator (KPI) to measure the performance improvement. Which KPI would be suitable to use?

Options:

A.

Percentage of on-time in full

B.

Percentage of rejects and returns

C.

Percentage of cost reduction

D.

Percentage of customer complaints

Question 3

Royal Naval Hospital at Rockstown, Anyport manages a fleet of nine ambulance vehicles. During busy periods, it becomes very difficult to keep track of the location of each ambulance (and the nature of their journey). Continual problems lead to the proposal for a new control system (ERNS).

For this ERNS project, the procurement department has drafted a specification in which only a bullet point list of basic requirements was written down. The procurement manager understands that the specification should be developed more specifically but a cross functional team from the Hospital could not do that. A senior buyer suggests that some of Hospital's pre-qualified suppliers could support them in developing the specification.

Which of the following should be a priority approach of procurement department in developing dialogue with those suppliers about specification development?

Options:

A.

Internal discussion

B.

General networking

C.

One-to-one meeting with the suppliers

D.

Request for quotation from the suppliers