New Year Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Last Attempt L4M3 Questions

Page: 5 / 17
Total 233 questions

Commercial Contracting Questions and Answers

Question 17

ABC Ltd is a UK based company. It plans to enter into a contract with XYZ Ltd which is based in Singapore. Which of the following are the mandatory elements for the contract between ABC Ltd and XYZ Ltd to be legally binding? Select THREE that apply.

Options:

A.

All parties must have capacity to contract

B.

The two parties must have intention to be bound

C.

The invitation to tender must be sent by the agreed deadline

D.

There must be an offer and an acceptance

E.

An amount of money must be paid upfront

F.

There must be an invitation to treat

Question 18

Curnoe Ltd supplied tyres to Garage Ltd. Garage Ltd agreed in the contract that for any specified breaches of contract, it would pay Curnoe Ltd £5 per tyre sold in breach. It subsequently sold tyres at below the listed price, which was one of the breaches mentioned in the contract. What is the £5 per tyre provision an example of?

Options:

A.

Quantum meruit

B.

Exclusion clause

C.

Liquidated damages

D.

Unliquidated damages

Question 19

Which of the following is an example of liquidated damages clause?

1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."

2. “If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"

3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."

4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"

Options:

A.

2 and 4 only

B.

1 and 3 only

C.

3 and 4 only

D.

1 and 2 only

Question 20

Which of the following are the 'fundamental' labour standards laid down by the International Labour Organisation?

1. Elimination of child labour

2. Payment of a minimum wage

3. The right to collective bargaining

4. Abolition of forced labor

Options:

A.

1, 2 and 4 only

B.

2, 3 and 4 only

C.

1, 3 and 4 only

D.

1, 2 and 3 only

Page: 5 / 17
Total 233 questions