Question 9

An Implementation Engineer is installing a second DirectFlash Shelf (DFS) on a FlashArray//XR4 controller. How should the Implementation Engineer complete the installation?

Options:

A.

Install a DFS card in PCIe Slot 0 and use these ports for Shelf connectivity.

B.

Install a DFS card in PCIe slot 4 and use it to connect the second DirectFlash Shelf.

C.

Install a DFS card in PCIe slot 3 and use it to connect the second DirectFlash Shelf.

Question 10

Before installing array rails, where should the cage nuts be placed?

Options:

A.

Lowest square of lowest RU

B.

Lowest square of top RU

C.

Top square of the lowest RU

Question 11

An Implementation Engineer is planning to add a DirectFlash Shelf to a FlashArray//XL with an existing DirectFlash Shelf. Which PCIe slot must be used for shelf connectivity?

Options:

A.

0

B.

4

C.

6

Question 12

The Customer’s Implementation Workbook specifies that the SMTP reply is “outlook.microsoft.com:587”. What correction should be made for array initialization to be successful?

Options:

A.

Provide username and password.

B.

Prefix the URL with “https://”.

C.

Remove the port number.