Question 41

Which of the following are the typical defects found by static analysis tools?

a. Variables that are never used.

b. Security vulnerabilities.

c. Poor performance.

d. Unreachable code.

e. Business processes not followed.

Options:

A.

b, c and d are true; a and e are false

B.

a is true; b, c, d and e are false

C.

c, d and e are true; a and b are false

D.

a, b and d are true; c and e are false

Question 42

What if the project isn't big enough to justify extensive testing..?

Options:

A.

Use risk based analysis to find out which areas need to be tested

B.

Use automation tool for testing

C.

Both a and b

D.

None of the above

Question 43

Which of the following product risks would be most effectively addressed just by static testing? 3 credits

Options:

A.

In the delivered application, one of the countries, as specified in the requirements, has not been correctly implemented.

B.

The application takes too long to process a request for additional cover.

C.

The test cases do not cover the key requirements.

D.

The successful bidder may not deliver all the required functionality on time.

Question 44

The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses. Which of the following checkpoints would be appropriate? 2 credits

Options:

A.

The bidder’s test policy should enforce that incident management fully conforms to IEEE 1044.

B.

The bidder’s project strategy shows that the data content of all the test environments conforms to EU standards.

C.

The bidder’s test plan shows that the application will be delivered for acceptance in six months time.

D.

The bidder’s project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a guide.