Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Newly Released ISTQB CTFL-Foundation Exam PDF

ISTQB Certified Tester Foundation Level Questions and Answers

Question 25

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a. Any deviation from the procedures described in the test strategy document

b. The overall estimated costs, timescales and resource requirements

c. A detailed schedule of testing activities

d. The development deliverables to be tested

e. Which test staff members (names) will be involved and when

f. Level of requirements coverage achieved

Which THREE of the above mentioned characteristics relate to the master test plan? 1 credit

Options:

A.

a

B.

b

C.

c

D.

d

E.

e

F.

f

Question 26

As part of the test strategy, entry and exit criteria will be defined for each test level. Which is NOT a valid reason for using entry and exit criteria? 1 credit

Options:

A.

The expectation is that development testing is not adequate.

B.

Exit criteria are used to decide on when to stop testing.

C.

Entry and exit criteria are a principal way for getting adequate resources.

D.

Using entry and exit criteria will prevent software that is not or poorly tested from going to the next test level.

Question 27

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:

a. Any deviation from the procedures described in the test

b. strategy document

c. The overall estimated costs, timescales and resource

d. requirements

e. A detailed schedule of testing activities

f. The development deliverables to be tested

g. Which test staff members (names) will be involved and when

h. Level of requirements coverage achieved

Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit

Options:

A.

a

B.

b

C.

c

D.

d

E.

e

F.

f

Question 28

Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits

Options:

A.

Criteria A = OK, criteria B = OK, criteria C = OK

B.

Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK

C.

Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK

D.

Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK