Question 37

Risks should be constantly reviewed. Given the current situation, which one of the following factors is most likely to lead to a revised view of product risk? 3 credits

Options:

A.

The concerns over the user interface may lead to changes to the interface which cannot be implemented by development in time for the second test iteration.

B.

The concerns over the user interface raises the likelihood of a risk in that area and increases the amount of test effort needed for the user interface, thereby limiting the test effort available for other parts of the test management tool.

C.

The delivery of the application without the interface changes may upset the user community.

D.

The method used for test estimation is not accurate enough and hence the money spent on testing exceeded its budget.

Question 38

Which of the following is a project risk mitigation step you might take as test manager? 1 credit

Options:

A.

Testing for performance problems

B.

Hiring a contractor after a test analyst leaves the company

C.

Arranging a back-up test environment in case the existing one fails during testing

D.

Performing a project retrospective meeting using the test results after each increment

Question 39

Which test management control option is most appropriate to adopt under these circumstances? 2 credits

Options:

A.

Introduce mandatory evening and weekend working to retrieve the 3 week slippage.

B.

Reconsider the exit criteria and review the test plan in the context of the current situation.

C.

Advise the user community regarding the reduced scope of requirements and the additional incremental delivery.

D.

Arrange a meeting with the user community representatives to discuss the user interface.

Question 40

Acceptance test cases are based on what?

Options:

A.

Requirements

B.

Design

C.

Code

D.

Decision table