Question 41

The degree of risk shared between the buyer and seller is determined by the:

Options:

A.

contract type.

B.

sponsors.

C.

project manager.

D.

stakeholders.

Question 42

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Question 43

The role of the _____ can be invaluable in problem solving.

Options:

A.

dominator

B.

devils advocate

C.

recognition seeker or dominator

D.

topic jumper

E.

recognition seeker

Question 44

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed.

Which activities have float available?

Options:

A.

Activity A has two weeks’ float, activity F has one week.

B.

Activity F has one-week float.

C.

There is no float available in the project.

D.

Activity A has eight weeks’ float.