Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

ISEB-PM1 BCS Exam Lab Questions

Page: 10 / 23
Total 625 questions

BCS Foundation Certificate in IS Project Management Questions and Answers

Question 37

Earned value measurement is an example of:

Options:

A.

Performance reporting.

B.

Planning control.

C.

Ishikawa diagrams.

D.

Integrating the project components into a whole.

Question 38

According to Herzberg, which of the following is a motivational factor?

Options:

A.

Working conditions

B.

Achievement

C.

Vacation time

D.

Pay

E.

Hygiene needs

Question 39

The sponsor is worried about the seller deriving extra profit on the cost plus fixed fee (CPFF) contract. Each month the sponsor requires the project manager to submit CPI calculations and an analysis of the cost to complete. The project manager explains to the sponsor that extra profits should NOT be a worry on this project because:

Options:

A.

The team is making sure the seller does not cut scope.

B.

All costs invoiced are being audited.

C.

There can only be a maximum 10 percent increase if there is an unexpected cost overrun.

D.

The fee is only received by the seller when the project is completed.

Question 40

Parametric Estimating is done as a part of which process:

Options:

A.

Estimate Activity Durations

B.

Sequence Activities

C.

Develop Schedule

D.

Estimate Activity Resources

Page: 10 / 23
Total 625 questions