Question 73

Your project team consists of 12 people in the same building you're located in, 4 people from the West Coast office, 2 people from the Kansas City office, and 6 people from the London office. Your office works different hours than all the other offices. Additionally, not all of the resources in your building are available at the same times during the day. Three of the 12 team members work swing shift hours. You use tools like web conferencing and email to distribute information to the team.

Which of the following is true?

Options:

A.

This question describes resource availability from the Develop Project Team process and information distribution methods from the Information Distribution process.

B.

This question describes the staffing management plan from the Acquire Project Team process and communication skills from the Information Distribution process.

C.

This question describes project staff assignments from the Develop Project Team process and communication skills from the Information Distribution process.

D.

This question describes virtual teams from the Acquire Project Team process and information distribution methods from the Information Distribution process.

Question 74

Which of the following lists contain processes that are included within Project Procurement Management?

Options:

A.

Plan purchases and acquisitions, plan contracting, request seller responses, select sellers

B.

Plan purchases and acquisitions, request seller responses, select sellers, schedule control

C.

Plan purchases and acquisitions, acquire project team, request seller responses, select sellers

D.

Plan purchases and acquisitions, acquire project team, contract approval, select sellers

Question 75

The project manager and project sponsor are discussing the project costs and whether it is better to have their own company do part of the project or hire another company to do the work. If they asked for your opinion, you might say it would be better to do the work yourself if:

Options:

A.

There is a lot of proprietary data.

B.

You have the expertise, but you do not have the available manpower.

C.

You do not need control over the work.

D.

Your company resources are limited.

Question 76

What tool and technique is used to determine whether work and deliverables meet requirements and product acceptance criteria?

Options:

A.

Decomposition

B.

Benchmarking

C.

Inspection

D.

Checklist analysis