Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

BCS ISEB-PM1 Based on Real Exam Environment

Page: 17 / 23
Total 625 questions

BCS Foundation Certificate in IS Project Management Questions and Answers

Question 65

Based on the network diagram in the chart, the resource working on activity G is replaced with another resource with 50 percent of the productivity of the previous resource.

How long will this project take?

Options:

A.

44

B.

51

C.

52

D.

36

Question 66

A contract change control system defines which of the following?

Options:

A.

Process by which the procurement is being satisfied

B.

Process by which the procurement can be modified

C.

Process by which the procurement can be obtained

D.

Process by which the procurement can be disposed

Question 67

Management by objectives assumes that the team ____________.

Options:

A.

Both 1) is receptive to an unstructured environment, and 2) possesses a self-fulfillment philosophy

B.

possesses a self-fulfillment philosophy

C.

All of the other alternatives apply

D.

is receptive to an unstructured environment.

E.

does not require close supervision

Question 68

A non-critical path activity is completed in half the time. Then, ___________.

Options:

A.

All of the other alternatives apply.

B.

The slack in the path containing this activity will increase.

C.

The total cost for this activity has decreased.

D.

The critical path is also reduced.

E.

Manpower from this activity can be assigned to other activities.

Page: 17 / 23
Total 625 questions