Question 85

Who is responsible for issuing the project charter?

Options:

A.

The project sponsor

B.

The senior Project Manager

C.

The project team

D.

The project manager

Question 86

You are in the middle of a major new facility construction project. The structural steel is in place and the heating conduits are going into place when a senior manager informs you that he is worried that the project will not meet the quality standards.

What should you do in this situation?

Options:

A.

Assure senior management that during the Plan Quality process it was determined that the project would meet the quality standards.

B.

Analogously estimate future results.

C.

Form a quality assurance team.

D.

Check the results from the last quality management plan.

Question 87

Which of the following MUST NOT performed in project initiation process?

Options:

A.

identify the requirements.

B.

identify business need.

C.

create project scope statement.

D.

create project charter.

Question 88

Information collected on the status of project activities being performed to accomplish the project work is known as what?

Options:

A.

Project management information system

B.

Work performance information

C.

Work breakdown structure

D.

Variance analysis

Page: 22 / 23