After all the due diligence is carried out, before awarding contract to the best supplier, sometimes procurement professionals find themselves in some problem solving situation; this might have been emanated from supplier facing a financial challenge or problems from external environment. Responding to this might require an amendment or an addendum, depending on the case in hand.
An amendment is for a physical change in the existing contract for example; if a contract contains a negotiated and agreed fixed price for the period of the contract but unexpected market forces such as an economic down turn or force majeure occur, the supplier may have to request an amendment order to continue to make a profit.
An addendum is when an additional document is added to the existing contract for example, If a contract have a schedule of rates and the market forces prices up, an addendum can be added to an existing contract with a revised schedule. Once accepted, the addendum becomes part of the con-tract. Addendum are physically used when the forecasted cost of a project rises and approval is needed to increase the contract spend.
Question 2
What is commissioning?
Options:
Answer:
Answer:
See the answer in explanation.
Explanation:
Explanation:
Commissioning is bringing something new into working condition, e.g start running a gas plant after building it. Commissioning is one of the eight elements that form the cycle of whole life asset management. The commissioning of an asset has the following associated costs, installation, training insurance, testing, operational efficiencies/performance and quality.
Question 3
What is contract performance review and continuous improvement?
Options:
Answer:
Answer:
See the answer in explanation.
Explanation:
Explanation:
Contract performance review and continuous improvement is the stage 11 of the CIPS procurement and supply cycle.
In order to effectively manage supplier performance and contractual obligations, the suppliers per-formance against key performance indicators (KPI) should be reviewed regularly. This KPI should have been agreed doing the post contract award negotiation. In addition to review KPIs suppliers and the procurement team should work towards continuous improvement. This is a continuous ef-fort to improve product or services within an organization. This may involve improving quality, reducing waste in the supply chain and focusing on innovation. It is an ongoing process that works toward perfection.