Question 33

(Which two statements are correct for the FIDIC Red Book (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The Contract includes the General Conditions and Particular Conditions, and no other documentation.

B.

Conditions of Contract means these General Conditions as amended by Particular Conditions.

C.

Contract Data is part of General Conditions of Contract.

D.

Contract Agreement, Letter of Acceptance and Letter of Tender are part of the Contract.

Question 34

(Which two answers show characteristics of Test on Completion or Test After Completion under the FIDIC Silver Book (edition 1999)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

In case of failure of the Test on Completion, the Employer may accept the Works, thereby reducing the Contract Price.

B.

The Employer can either opt for Tests on Completion or Tests after Completion, but not both.

C.

Tests after Completion are carried out by the Employer.

D.

Although Tests after Completion fail, it may be considered as passed when performance damages specified in the contract are paid by the Contractor.

Question 35

Which one statement regarding the adjustment of the Contract Price as mentioned in Sub-Clause 13.8 of FIDIC Silver Book (edition 1999) is correct?

Options:

A.

If the Contract Price is to be adjusted for rises and falls in the cost of labour, the Contractor is entitled to compensation in such a way that all rises and falls in the costs are compensated fully.

B.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. This can result in lower adjustments of the Contract Price than the actual changes in the costs of labour and/or Goods.

C.

If Particular Conditions provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8, it can only apply to rises or falls in the costs of labour and Goods.

D.

The Particular Conditions can provide a calculation method or refer to a specific set of index for adjustments following Sub-Clause 13.8. Only the Base Date can be taken as the date from which the adjustment should be calculated from.

Question 36

Under the FIDIC Red Book (edition 1999): the Contractor submitted Final Statement in accordance with the Contract and the Contractor wants to correct it. Can the Contractor correct the Final Statement?