Certified Contract Manager Questions and Answers

Question 21

The Contractor is entitled to an advance payment, it has obtained such payment and it has not yet been entirely paid back. Under FIDIC Red Book (edition 1999), in which two situations will the outstanding balance of the advance payment become immediately due?

Choose all of the correct answers (multiple possibilities).

Options:

A.

If the advance payment is not completely repaid before Time for Completion.

B.

If advance payment is not completely repaid before the Performance Certificate is issued.

C.

If the advance payment is not completely repaid before the Taking-Over Certificate is issued.

D.

If the advance payment is not completely repaid before termination of the Contract.

Question 22

Under the FIDIC Red Book, which one of the following statements is correct for a claim by the Contractor?

Options:

A.

The Employer has the authority to accept a claim by the Contractor, even in the case of the Contractor ' s failure to comply with the notice requirements.

B.

If the Engineer does not make a determination, the Employer and the Contractor are unable to agree to settle an issue that gave rise to a claim.

C.

The Engineer ' s response to the Contractor ' s submission of detailed particulars that are required by the procedure for claims by the Contractor must include the Engineer ' s final decision on the quantum.

D.

It is the Employer ' s Representative who must first respond to the claim by the Contractor.

E.

The Engineer ' s response to a claim by the Contractor is final and binding upon the Employer.

Question 23

Which two statements are correct regarding the FIDIC Red Book (edition 2017)?

Options:

A.

Words and expressions stated in Sub-Clause 1.1 Definitions do not apply in respect of Specifications and Drawings.

B.

Contract Data contains information which is required by certain Sub-Clauses in the General Conditions.

C.

There is never a difference in effect whether in the Particular Conditions when the term " Works " is used, or when the term " works " is used.

D.

In some cases, if a certain information is not provided in the Contract Data, the relevant Sub-Clause shall not be applicable.

Question 24

(Which two of the following statements are correct regarding the first step of an Employer ' s Claim, considering that the Employer is entitled to a reduction in the Contract Price and/or an extension of the Defects Notification Period under any Clause of the Conditions of Contracts or otherwise in connection with the Contract, under the FIDIC Red, Yellow, and Silver Books (edition 2017)?

Choose all of the correct answers (multiple possibilities).)

Options:

A.

The Employer shall give a Notice to the Engineer, describing the event or circumstance giving rise to the cost, loss, delay or extension of the Defects Notification Period for which the Claim is made.

B.

The Notice shall be given to the Engineer, as soon as practicable, and no later than 28 days after the claiming Party became aware, or should have become aware, of the event or circumstance.

C.

A Notice from the Employer is not required in order to give a Notice to the Engineer for services requested by the Contractor.

D.

The Notice given by the Employer must also include the legal or contractual basis of the claim, including the clause of the Contract under which it is made.