Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CCM Exam Questions Tutorials

Page: 5 / 8
Total 100 questions

Certified Contract Manager Questions and Answers

Question 17

Under the FIDIC Red Book (edition 2017), the Engineer has suspended works to come to a change of the design of a part of the Works. After expiry of 84 days of suspension, the Contractor gave notice thereof. Following this notice, the suspension was not lifted within 28 days. What two statements are correct in such a situation?

Options:

A.

Under the Contract the Parties cannot agree on further suspension and the Contractor may immediately terminate the Contract if it affects the whole Works.

B.

The Contractor cannot terminate the Contract.

C.

The Contractor may terminate the Contract if it affects the whole Works, but only after it has given a second notice to the Engineer.

D.

The Contractor may omit the affected part of Works and deny to carry out such Work going forward, but only after it has given a second notice to the Engineer.

Question 18

Under the FIDIC Construction Contract, which one of the following statements is correct?

Options:

A.

Payments of a DAB Member's retainer fee is the sole responsibility of the Contractor.

B.

For an ad-hoc DAB, a retainer fee for each DAB Member must be paid to the Member on the first day of each calendar month.

C.

Payment to DAB Members must be certified by the Employer.

D.

If all persons nominated to serve as members of an ad hoc DAB do not sign a DAB Agreement, an appointing entity can make appointments.

E.

A DAB must give its decision in writing on any dispute when requested by one of the Parties.

Question 19

Is the Employer obliged under FIDIC Silver Book (edition 1999) to describe which Documents are to be submitted to the Employer? (1 correct response applies)

Options:

A.

No, according to Sub-Clause 5.7 provisional operation and maintenance manuals are always required.

B.

No, because the Contractor has a duty to supply the Employer with every Document, given Sub-Clause 7.4.

C.

Yes, because otherwise the Contractor doesn't have to submit any Document until Completion of the Works as stated in Sub-Clause 1.8.

D.

Yes, the Employer should define which documents it wants to receive from the Contractor as Contractor's Documents in the Employer's Requirements, as stated in Sub-Clause 5.2.

Question 20

Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

Options:

A.

Letter of Acceptance

B.

Letter of Intent

C.

Memorandum of understanding

D.

Letter of Intent & Memorandum of understanding

Page: 5 / 8
Total 100 questions