Question 9

You are the new Contract Manager of the Contractor in a bridge project using FIDIC Yellow Book (edition 2017). The project had been suspended due to a material change in the Employer ' s financial arrangement. You have worked with your team to identify several failures of the Employer in carrying its obligations under the Contract. Which one of the following does NOT allow the Contractor to issue Notice to terminate the Contract?

Options:

A.

A prolonged suspension for more than 1 year has affected the whole of the Works.

B.

The Contractor does not receive the amount due under the latest Payment Certificate for more than 4 months after the due date.

C.

The Contractor has requested the Employer but has not received any evidence that the financial arrangement is being maintained, despite having sent a notice thereto 4 months earlier.

D.

The Employer failed to comply with a final and binding determination issued by the Engineer, and such failure constitutes a material breach of the Employer ' s obligations under the Contract.

Question 10

(Sub-Clause 12.3(a) of FIDIC Red Book (edition 1999) specifies four criteria which are applicable without reference to Clause 13. A new rate shall only be appropriate if all four criteria are satisfied. Is this statement true or false?)

Options:

A.

True

B.

False

Question 11

The details of all the matters that have been clarified and agreed between the Employer and tenderers during the tender stage are recorded by, for instance, a memorandum of understanding. The Employer may award the contract to the tenderer through a letter of formal acceptance, signed by the Employer. This process is in compliance with which one of the following Golden Principles (GP ' s)?

Options:

A.

GP 3

B.

GP 1

C.

GP 2

D.

GPA

Question 12

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?

Choose all of the correct answers (multiple possibilities).

Options:

A.

The appointment of the Contractor and receipt of the Advance Payment Guarantee, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 14.2.1.

B.

Receipt of a statement via a letter showing the amounts to which the Contractor considers itself to be entitled.

C.

The appointment of the Contractor ' s Representative and receipt of the Performance Security, by the Employer, in the form, and issued by an entity, in accordance with Sub-Clause 4.2.1.

D.

Receipt of a statement and supporting documents.