Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CCM Exam Dumps : Certified Contract Manager

PDF
CCM pdf
 Real Exam Questions and Answer
 Last Update: Apr 20, 2026
 Question and Answers: 140 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
CCM exam
PDF + Testing Engine
CCM PDF + engine
 Both PDF & Practice Software
 Last Update: Apr 20, 2026
 Question and Answers: 140
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
CCM Engine
 Desktop Based Application
 Last Update: Apr 20, 2026
 Question and Answers: 140
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Certified Contract Manager Questions and Answers

Question 1

You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.

The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.

1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.

The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.

What is the correct Commencement Date?

Options:

A.

12 June 2022

B.

15 June 2022

C.

15 July 2022

D.

1 August 2022

Buy Now
Question 2

FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?

Options:

A.

True

B.

False

Question 3

Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

Options:

A.

Letter of Acceptance

B.

Letter of Intent

C.

Memorandum of understanding

D.

Letter of Intent & Memorandum of understanding