Verified By IT Certified Experts
CertsTopics.com Certified Safe Files
Up-To-Date Exam Study Material
99.5% High Success Pass Rate
100% Accurate Answers
Instant Downloads
Exam Questions And Answers PDF
Try Demo Before You Buy
You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition 2017), with Time for Completion of 5 months.
The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
What is the correct Commencement Date?
FIDIC Red, Yellow, and Silver Books (both editions) contain a provision for the Engineer or Employer to instruct the Contractor to employ a subcontractor, thereby also permitting the Contractor to refuse to employ such proposed subcontractor on the basis of a reasonable objection by a notice. Is this statement true or false?
Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?