Spring Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

CCM Exam Dumps : Certified Contract Manager

PDF
CCM pdf
 Real Exam Questions and Answer
 Last Update: Feb 24, 2026
 Question and Answers: 100 With Explanation
 Compatible with all Devices
 Printable Format
 100% Pass Guaranteed
$25.5  $84.99
CCM exam
PDF + Testing Engine
CCM PDF + engine
 Both PDF & Practice Software
 Last Update: Feb 24, 2026
 Question and Answers: 100
 Discount Offer
 Download Free Demo
 24/7 Customer Support
$40.5  $134.99
Testing Engine
CCM Engine
 Desktop Based Application
 Last Update: Feb 24, 2026
 Question and Answers: 100
 Create Multiple Test Sets
 Questions Regularly Updated
  90 Days Free Updates
  Windows and Mac Compatible
$30  $99.99

Verified By IT Certified Experts

CertsTopics.com Certified Safe Files

Up-To-Date Exam Study Material

99.5% High Success Pass Rate

100% Accurate Answers

Instant Downloads

Exam Questions And Answers PDF

Try Demo Before You Buy

Certification Exams with Helpful Questions And Answers

Certified Contract Manager Questions and Answers

Question 1

The amount of an advance payment guarantee provided for pursuant to FIDIC Red and Yellow Books (both editions) may be reduced as of:

Options:

A.

The Commencement Date

B.

The date of the Taking Over Certificate

C.

The date on which the entire advance payment is repaid as stated in the Payment Certificate

D.

The date on which an amount is repaid by the Contractor as stated in the Payment Certificates

Buy Now
Question 2

Which of the following FIDIC contract forms require certification in the payment process? (2 correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

FIDIC Conditions of Contract for Construction ("Red Book").

B.

FIDIC Conditions of Contract for Plant and Design Build ("Yellow Book").

C.

FIDIC Conditions of Contract for EPC/Turnkey Projects ("Silver Book").

Question 3

Under FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the revised programme?

Choose all of the correct answers (multiple possibilities)

Options:

A.

All internationally recognized holiday periods.

B.

The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).

C.

The sequence and timing of the remedial work.

D.

Only the delivery dates of Plant and Materials which have not been delivered on Site yet.