Question 41

Which one of the following documents constitutes a contract and is considered binding on both parties, when the Employer wants to award the Contract to the tenderer?

Options:

A.

Letter of Acceptance

B.

Letter of Intent

C.

Memorandum of understanding

D.

Letter of Intent & Memorandum of understanding

Question 42

(Under the FIDIC Red, Yellow, and Silver Books (1999 editions), the Engineer/Employer shall be entitled to withhold from the release of retention money the estimated cost of any work which remains to be executed under Clause 11 (Defects Liability) in the Red Book or under Clause 12 (Tests after Completion) in the Yellow and Silver Books. Is this statement true or false?)

Options:

A.

True

B.

False