Pre-Summer Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Passed Exam Today CCM

Page: 7 / 11
Total 140 questions

Certified Contract Manager Questions and Answers

Question 25

(Golden Principle 2 states that " The Particular Conditions must be drafted clearly and unambiguously. " Which statement best underlines this Golden Principle in relation to the FIDIC Red, Yellow, and Silver Books (both editions)?)

Options:

A.

Clarifications to the meaning of tender documents together with answers to tenderers’ inquiries made during the tender period by the Employer can be inconsistent. If Sub-Clause 1.5 does not provide for the right order, this Sub-Clause can be amended explicitly or implicitly, and this can be done through any of the documents mentioned in Sub-Clause 1.5.

B.

When clarifications are given during the tender period, which might impact several general conditions, it is not necessary to amend all these conditions through the Particular Conditions or to consider which exact general conditions require amendment, as such clarifications are deemed to be self-explanatory.

C.

Modifications made to the Conditions of Contract during tender negotiations that were only documented in emails between the Parties can be part of the Contract as long as those emails are subsequently included in the List of Contract documents. In such a case, it is not necessary to incorporate those modifications in, for instance, the Particular Conditions.

D.

In the Particular Conditions, all changes to the General Conditions must be clearly identified by reference to specific Sub-Clause numbers. Additionally, the Particular Conditions Sub-Clauses must clearly indicate the relationship between the newly introduced text and the corresponding General Conditions Sub-Clauses’ original text, e.g., addition, omission, replacement, or amendment.

Question 26

You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017). The Employer demands perfection in the project ' s design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?

Options:

A.

The Contractor submits a Value Engineering proposal regarding the lighting system for the operation rooms. The Engineer is positive about the proposal and tells the Contractor they need to look into it.

B.

The Engineer instructs a change in slopes of the access road to the intensive care unit to meet the Employer ' s Requirement. The Engineer does so with a Notice in accordance with Sub-Clause 3.5.

C.

The Engineer requests a proposal regarding a change in type of windows and doors. The Contractor submitted the proposal accordingly to the Engineer. The Engineer instructs the Variation.

D.

The Employer verbally instructs a change in the type of doors. The Engineer issued a Notice describing the required change and denying any costs for the Contractor.

Question 27

Under the FIDIC Red Book (edition 1999), as part of the Contractor submission of Statement, any amount to be deducted for retention, will be calculated by applying the percentage of retention stated in the Appendix to Tender to the total of: (two correct answers apply)

Choose all of the correct answers (multiple possibilities).

Options:

A.

The estimated contract value of the Works executed.

B.

Any amounts to be added and/or deducted for the advance payment and repayments under Sub-Clause 14.2.

C.

Any amounts to be added and deducted for changes in legislation and changes in cost.

D.

Any amounts to be added and deducted for Plant and Materials in accordance with Sub-Clause 14.5.

Question 28

In the FIDIC Silver Book (both editions), the Notice of the Commencement Date will be informed by whom? (1 correct response applies)

Options:

A.

The Engineer

B.

The Engineer ' s Resident Engineer

C.

The Employer

D.

The Employer ' s Representative

Page: 7 / 11
Total 140 questions