Amazon AWS Certified Advanced Networking - Specialty Questions and Answers

Question 45

A company is planning a migration of its critical workloads from an on-premises data center to Amazon EC2 instances. The plan includes a new 10 Gbps AWS Direct Connect dedicated connection from the on-premises data center to a VPC that is attached to a transit gateway. The migration must occur over encrypted paths between the on-premises data center and the AWS Cloud.

Which solution will meet these requirements while providing the HIGHEST throughput?

Options:

A.

Configure a public VIF on the Direct Connect connection. Configure an AWS Site-to-Site VPN connection to the transit gateway as a VPN attachment.

B.

Configure a transit VIF on the Direct Connect connection. Configure an IPsec VPN connection to an EC2 instance that is running third-party VPN software.

C.

Configure MACsec for the Direct Connect connection. Configure a transit VIF to a Direct Connect gateway that is associated with the transit gateway.

D.

Configure a public VIF on the Direct Connect connection. Configure two AWS Site-to-Site VPN connections to the transit gateway. Enable equal-cost multi-path (ECMP) routing.

Question 46

A company is hosting an application on Amazon EC2 instances behind a Network Load Balancer (NLB). A solutions architect added EC2 instances in a second Availability Zone to improve the availability of the application. The solutions architect added the instances to the NLB target group.

The company's operations team notices that traffic is being routed only to the instances in the first Availability Zone.

What is the MOST operationally efficient solution to resolve this issue?

Options:

A.

Enable the new Availability Zone on the NLB

B.

Create a new NLB for the instances in the second Availability Zone

C.

Enable proxy protocol on the NLB

D.

Create a new target group with the instances in both Availability Zones

Question 47

A company's application team is unable to launch new resources into its VPC. A network engineer discovers that the VPC has run out of usable IP addresses. The VPC CIDR block is 172.16.0.0/16.

Which additional CIDR block can the network engineer attach to the VPC?

Options:

A.

172.17.0.0/29

B.

10.0.0.0/16

C.

172.17.0.0/16

D.

192.168.0.0/16

Question 48

A company has a total of 30 VPCs. Three AWS Regions each contain 10 VPCs. The company has attached the VPCs in each Region to a transit gateway in that Region. The company also

has set up inter-Region peering connections between the transit gateways.

The company wants to use AWS Direct Connect to provide access from its on-premises location for only four VPCs across the three Regions. The company has provisioned four Direct

Connect connections at two Direct Connect locations.

Which combination of steps will meet these requirements MOST cost-effectively? (Select THREE.)

Options:

A.

Create four virtual private gateways. Attach the virtual private gateways to the four VPCs.

B.

Create a Direct Connect gateway. Associate the four virtual private gateways withthe Direct Connect gateway.

C.

Create four transit VIFs on each Direct Connect connection. Associate the transit VIFs with the Direct Connect gateway.

D.

Create four transit VIFs on each Direct Connect connection. Associate the transit VIFs with the four virtual private gateways.

E.

Create four private VIFs on each Direct Connect connection to the Direct Connect gateway.

F.

Create an association between the Direct Connect gateway and the transit gateways.

Page: 12 / 21
Total 288 questions