Where is the proper place to put a vapor barrier in a cold climate?
In which of the following locations in concrete masonry should a control joint be placed?
In coordination of construction documents, heating duct clearances and tolerances in suspended ceiling plenum spaces should be cross-checked with the mechanical engineer and which one of the following?
During CD phase, the architect notices plumbing lines clash with roof trusses. What should the architect do first?