Question 13

During an analysis of an existing sanitary sewer crossing a proposed building site, it was determined that the outflow invert at one manhole was 120 feet and the inflow invert at the next manhole, which is 200 feet downstream, was 117 feet.

What is the percentage of slope between the two manholes?

Options:

A.

1.5%

B.

2%

C.

3%

Question 14

In winter conditions, when the outdoor air is below freezing and the indoor humidity is maintained at 40 percent relative humidity for 24 hours a day, ice forms on the exterior surface of the stone facing.

Which of the following elements is missing from the building wall section?

Options:

A.

Vapor barrier

B.

Wall insulation

C.

Air space

D.

Rain screen

Question 15

Refer to the exhibit.

What is the purpose of the flexible connection in the fan coil shown?

Options:

A.

To provide a field point of connection of the ductwork to the fan coil unit

B.

To insulate against heat transfer from the fan coil unit

C.

To minimize sound transfer

D.

To transition from the fan coil unit flange to the desired duct size

Question 16

Refer to the exhibit.

An architect is working on an airport lounge project. The 9,000 SF floor plan includes an open, double-height space. Due to area limitations, all program requirements cannot fit within the 9,000 SF floor plan. A mezzanine level with one exit is being proposed to solve this programming constraint. There are adequate exits available on the main floor plan to pick up the additional occupant load from the mezzanine.

Which method of mezzanine construction should the architect design?

Options:

A.

2,500 SF open lounge area for 20 people

B.

2,750 SF enclosed business center for 15 people

C.

3,250 SF open dining area for 30 people

Page: 4 / 8