Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

Architect Registration Examination Changed Project-Planning-Design Questions

ARE 5.0 Project Planning & Design (PPD) Questions and Answers

Question 21

For a three-story building, which of the following is considered a vertical irregularity with respect to seismic design?

Options:

A.

The effective mass of the roof is one-half the mass of the floor immediately below.

B.

The building has a significant reentrant corner on the front side.

C.

The effective mass of story 2 is two times the mass of story 1.

D.

Interior symmetrically placed shear walls are four times as stiff as perimeter columns.

Question 22

A multistory warehouse is to be converted into a high-tech office building. The owners propose a variety of services and flexibility to tenants, including cable/internet, fiber optic communications, dish/satellite, and security systems.

In order to accommodate this broad array of electronic and communications services, the architect should recommend which of the following electrical and communications distribution systems?

Options:

A.

Poke-through system

B.

Cellular deck system

C.

Raised access floor system

D.

Flat cable wiring system

Question 23

To reduce embodied energy in a 500-unit redevelopment, the architect should create a strategy to include which of the following? Check the three that apply.

Options:

A.

Re-use existing buildings and structures wherever possible

B.

Orient the building to create transitional spaces within the development

C.

Construct buildings and infrastructure from local and low-energy materials where possible

D.

Decrease the percentage of high-rise units

E.

Increase the percentage of single-story units

F.

Use simple geometric structures

Question 24

An elementary school requires a renovation, selective demolition, and a major addition in order to accommodate a growing student population. An architectural firm has prepared schematic design plans incorporating the school's increased programmatic needs, including an enlarged library, cafeteria, and gymnasium; a secure courtyard; and additional space for administrative offices and classrooms. The main entrance was relocated in order to improve the traffic and pedestrian flow at the beginning and end of the school day, and additional parking was provided to comply with current zoning requirements.

The existing single-story masonry building was built in 1950. Two small additions were built later: the north addition will be kept and repurposed, but the south addition will be demolished. The building contains asbestos and lead in roof soffits, floor tiles, pipe insulation, and window paint. All existing mechanical systems need to be replaced; new systems have not been selected.

Considerations for the renovation include:

    The relocated front entrance must be easily recognizable, highly visible, and secure.

    Interior and exterior materials need to be durable and maintainable in order to withstand frequent student abuse, but also economical due to strict budget limitations.

    Good indoor air quality and increased energy efficiency are priorities for the selection of mechanical equipment.

After completion, the entire school should look uniform, without a distinctive difference between the existing building and new addition.

Building information:

    Construction Type is II-B.

The following resources are available for your reference:

    Existing Plans, including site and floor plans

    Proposed Plans, including site and floor plans

    Cost Analysis

    Zoning Ordinance Excerpts, for off-street parking requirements

    IBC Excerpts, showing relevant code sections

    ADA Standards Excerpts, showing relevant sections from the ADA Standards for Accessible Design

When the addition is completed, the school will be fully sprinkled per NFPA 13 Standard for the Installation of Sprinkler Systems requirements, with a continuous 24-foot wide fire access lane provided around the building perimeter.

Through a code analysis, the combination of construction type, occupancy, and building area present a compliance problem.

Options:

A.

Add firewall to design

B.

Check frontage area increase

C.

Reduce building area