Labour Day Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

SAP C_TS422_2021 Dumps

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

How can you achive a feasible production plan in case of capacity constraints?

Options:

A.

Select an alternative mode on a resource.

B.

Adjust the available capacity.

C.

Reduce the planning window

D.

Form optimum sequence to reduce setup times

E.

Execute an infinite production planning run

Question 2

You want to schedule an operation finitely, without moving other operations. Which scheduing strategy do you select?

Options:

A.

Schedule in working time only

B.

Squeeze in

C.

Insert operation

D.

Find slot

Question 3

An issue storage location was NOT found through the work center, bill of material(BOM) item, or material master. What determines whether the storage location can be derived from the production version?

Options:

A.

MRP group

B.

Plants parameters

C.

MRP controller

D.

MRP profile

Question 4

Your project used process orders for the production of liquid chemicals.

What can you define to ensure that the production flow happens only in physically connected tanks?

Options:

A.

Operation network

B.

Work center hierarchy

C.

Setup matrix

D.

Resource network

Question 5

When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?

Options:

A.

The cross-plant status

B.

The plant-specific status

C.

The last restrictive status

D.

The most restrictive status

Question 6

For what production type are production orders used?

Options:

A.

Process manufacturing processes

B.

Replenishment controlled by control cycles

C.

Discrete manufacturing processes

D.

Period and quantity-oriented production

Question 7

Which of the following elements does MRP take into account during net requirement calculation?

Options:

A.

Purchase orders

B.

Lot size

C.

Maximum stock level

D.

Safety stock

Question 8

Why would you use phantom assemblies?

Options:

A.

To simplify the structure of bills of materials

B.

To make the assignment of components easier

C.

To reduce the number of changes required in bills of materials

D.

To reduce the number of material masters

E.

To increase the number of planning levels

Question 9

Which of the following is valid sequence of the main activities in production order processing?

Options:

A.

Creation, availability check, release, material widrawal, confirmation

B.

Creation, release, printing, goods issue, confirmation, goods receipt

C.

Creation, printing, release, goods issue, confirmation, goods receipt

D.

Creation, release, settlement, goods issue, confirmation, goods receipt

Question 10

In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?

Options:

A.

MRP type

B.

MRP group

C.

MRP planning file

D.

MRP controller

Question 11

How can you carry out cost object controlling for production orders?

Options:

A.

Milestone-related

B.

Cost-related

C.

Product-related

D.

Order-related

Question 12

What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?

Options:

A.

Material Requirements Planning (MRP)

B.

Capacity Requirements Planning (CRP)

C.

Supply Network Planning (SNP)

D.

Demand Planning (DP)