Weekend Sale 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: save70

SAP C_TS422_2021 Exam With Confidence Using Practice Dumps

Exam Code:
C_TS422_2021
Exam Name:
SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing
Vendor:
Questions:
82
Last Updated:
Jul 5, 2025
Exam Status:
Stable
SAP C_TS422_2021

C_TS422_2021: SAP Certified Application Associate Exam 2025 Study Guide Pdf and Test Engine

Are you worried about passing the SAP C_TS422_2021 (SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing) exam? Download the most recent SAP C_TS422_2021 braindumps with answers that are 100% real. After downloading the SAP C_TS422_2021 exam dumps training , you can receive 99 days of free updates, making this website one of the best options to save additional money. In order to help you prepare for the SAP C_TS422_2021 exam questions and verified answers by IT certified experts, CertsTopics has put together a complete collection of dumps questions and answers. To help you prepare and pass the SAP C_TS422_2021 exam on your first attempt, we have compiled actual exam questions and their answers. 

Our (SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing) Study Materials are designed to meet the needs of thousands of candidates globally. A free sample of the CompTIA C_TS422_2021 test is available at CertsTopics. Before purchasing it, you can also see the SAP C_TS422_2021 practice exam demo.

SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing Questions and Answers

Question 1

When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?

Options:

A.

The cross-plant status

B.

The plant-specific status

C.

The last restrictive status

D.

The most restrictive status

Buy Now
Question 2

You want to schedule an operation finitely, without moving other operations. Which scheduing strategy do you select?

Options:

A.

Schedule in working time only

B.

Squeeze in

C.

Insert operation

D.

Find slot

Question 3

Your project used process orders for the production of liquid chemicals.

What can you define to ensure that the production flow happens only in physically connected tanks?

Options:

A.

Operation network

B.

Work center hierarchy

C.

Setup matrix

D.

Resource network