Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI-001 PMI Exam Lab Questions

Page: 13 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 49

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Question 50

An associate who calculates fees daily to support the department is doing which of the following?

Options:

A.

Phase work

B.

Project work

C.

Lifecycle work

D.

Operations work

Question 51

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project and for recording and communicating decisions?

Options:

A.

Project team

B.

Focus group

C.

Change control board

D.

Project stakeholders

Question 52

The Perform Integrated Change Control process occurs in which Process Group?

Options:

A.

Initiating

B.

Executing

C.

Monitoring and Controlling

D.

Planning

Page: 13 / 34
Total 918 questions