Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Legit PMI-001 Exam Download

Page: 16 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 61

Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

Options:

A.

Procurement documents

B.

Inspection and audits

C.

Estimate budget

D.

Risk register

Question 62

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Question 63

Which of the following is a tool or technique of the Define Activities process?

Options:

A.

Rolling wave planning

B.

Precedence diagramming method (PDM)

C.

Alternatives analysis

D.

Parametric estimating

Question 64

When are deliverables accepted or not accepted?

Options:

A.

When the project is initiated

B.

As an output of the scope verification process

C.

When the project is closing

D.

In the contract closure process

Page: 16 / 34
Total 918 questions