Project Management Professional v5 Questions and Answers

Question 5

A weighting system is a tool for which area of procurement?

Options:

A.

Plan contracting

B.

Request seller responses

C.

Select sellers

D.

Plan purchase and acquisition

Question 6

Which of the following is an example of push communication?

Options:

A.

Intranet sites

B.

Video conferencing

C.

Knowledge repositories

D.

Press releases

Question 7

The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?

Options:

A.

$800

B.

$1000

C.

$1250

D.

$1800

Question 8

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

Options:

A.

Supportive

B.

Directive

C.

Controlling

D.

Instructive