Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Free PMI-001 PMI Updates

Page: 4 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 13

Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?

Options:

A.

-8000

B.

-2000

C.

2000

D.

8000

Question 14

Which of the following is the correct network diagram for the table?

Options:

A.

Begin-A-C-D-E-End-B-D

B.

Begin-A-B-C-D-E-End

C.

Begin-A-B-D-E-End A-C-D

D.

Begin-A-C-D-E-End-B-C

Question 15

Which of the following is an output of the Perform Integrated Change Control process?

Options:

A.

Project document updates

B.

Organizational process assets updates

C.

Change requests

D.

Deliverables

Question 16

A project manager needs to deliver the project 2 weeks before the planned date without changing the scope. Which of the following techniques may be applied to reevaluate the schedule?

Options:

A.

What-if scenario analysis

B.

Critical chain method

C.

Schedule crashing

D.

Resource leveling

Page: 4 / 34
Total 918 questions