Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

PMI-001 Exam Questions Tutorials

Page: 19 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 73

Which of the following is a measure of the value of work completed compared to the actual cost or progress made on the project?

Options:

A.

Schedule performance index (SPI)

B.

Cost performance index (CPI)

C.

Cost variance (CV)

D.

Planned value (PV)

Question 74

When sequencing activities, what does the common acronym FF stand for?

Options:

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

Question 75

Which of the following is an output of Close Procurements?

Options:

A.

Accepted deliverables

B.

Organizational process assets updates

C.

Managing stakeholder expectations

D.

Performance reports

Question 76

The process for performing variance analysis may vary, depending on:

Options:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Page: 19 / 34
Total 918 questions