Weekend Sale Special - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: top65certs

Complete PMI-001 PMI Materials

Page: 25 / 34
Total 918 questions

Project Management Professional v5 Questions and Answers

Question 97

The organizational process assets that are of particular importance to Plan Communications are:

Options:

A.

Formal plans and procedures

B.

Lessons learned and historical information

C.

Guidelines and knowledge bases

D.

Stakeholder positions and their influence

Question 98

The milestone list is an input to which process from the Planning Process Group?

Options:

A.

Define Activities

B.

Estimate Activity Durations

C.

Estimate Activity Resources

D.

Sequence Activities

Question 99

What is an objective of the Develop Project Team process?

Options:

A.

Feelings of trust and improved cohesiveness

B.

Ground rules for interaction

C.

Enhanced resource availability

D.

Functional managers becoming more involved

Question 100

Which Project Time Management process includes bottom-up estimating as a tool or technique?

Options:

A.

Estimate Activity Resources

B.

Sequence Activities

C.

Estimate Activity Durations

D.

Develop Schedule

Page: 25 / 34
Total 918 questions