Question 45

Before submitting AV System drawings to external project stakeholders, the integrator should conduct an internal review of the drawings to ensure that _____.

Options:

A.

the lowest cost equipment that meets the client's need has been specified

B.

all of the required equipment is already in stock

C.

there are no discrepancies among the equipment list, drawings, and specifications

D.

all required system performance verification tests have been conducted

Question 46

What document is used to account for lost time due to other trades during a project?

Options:

A.

Punch list

B.

Daily Progress report

C.

RFI

D.

Submittals

Question 47

According to InfoComm best practices, why should you use pre-measured bolts when connecting a mounting bracket to a flat panel display?

Options:

A.

Bolts that are not pre-measured may pose a security risk

B.

Bolts that are too short will not secure the display

C.

Bolts that are too long can damage the mounting bracket

D.

Bolts that are too short can damage the wall

Question 48

Which of the following describes the number of cycles in a given time period?

Options:

A.

wavelength

B.

frequency

C.

amplitude

D.

Magnitude