Pass APM-001 Exam Guide

Page: 7 / 26
Total 704 questions

Associate in Project Management (APM) Questions and Answers

Question 25

Project Stakeholder Management focuses on:

Options:

A.

project staff assignments

B.

project tea m acquisition

C.

managing conflicting interests

D.

communication methods

Question 26

The following chart contains information about the tasks in a project.

Based on the chart, what is the cost variance (CV) for Task 6?

Options:

A.

-2,000

B.

0

C.

1,000

D.

2,000

Question 27

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

Options:

A.

Business case

B.

Work breakdown structure

C.

Requirements documentation

D.

Risk register

Question 28

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-D-G

B.

A-B-E-G

C.

A-C-F-G

D.

A-C-E-G

Page: 7 / 26
Total 704 questions