Question 33

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Question 34

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Question 35

When the business objectives of an organization change, project goals need to be:

Options:

A.

realigned.

B.

performed.

C.

improved.

D.

controlled.

Question 36

A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:

Options:

A.

Cost Plus Incentive Fee (CPIF).

B.

Fixed Price Incentive Fee (FPIF).

C.

Cost Plus Award Fee (CPAF).

D.

Fixed Price with Economic Price Adjustment (FP-EPA).

Page: 9 / 26