Question 93

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

Options:

A.

Supportive

B.

Leading

C.

Neutral

D.

Resistant

Question 94

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

Question 95

When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail using which type of estimating?

Options:

A.

Bottom-up

B.

Parametric

C.

Analogous

D.

Three-point

Question 96

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Options:

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan