Question 29

What test process is included as part of TPI Next? [1]

Options:

A.

Identify test specification

B.

Identify test environment

C.

Identify test execution

D.

Identify test conditions

Question 30

Your testing team has just received the test conditions for a new project. You are conducting Test Design activities for this project. Your team feels that it would be beneficial to create high-level test cases.

What should they do concurrently with creating these test cases? [2]

Options:

A.

Create the test plan.

B.

Create the test automation scripts.

C.

Create the test summary report for the test cases you are creating.

D.

Create the traceability between the test cases and the requirements.