Certified in Planning and Inventory Management (CPIM 8.0) Questions and Answers

Question 173

What priority control technique is most appropriate for a firm using a cellular production system?

Options:

A.

Shortest processing time (SPT) rule

B.

Distribution requirements planning (DRP)

C.

Pull production activity control (PAC)

D.

Push production activity control (PAC)

Question 174

An organization provides customer call center operations for major financial service organizations around the world. As part of a long-term strategy, the organization plans to add healthcare clients to the portfolio. In preparation for contract negotiations with new clients, to which cybersecurity framework(s) should the security team ensure the organization adhere?

Options:

A.

Frameworks that fit the organization’s risk appetite, as cybersecurity does not vary industry to industry

B.

Control Objectives For Information And Related Technology (COBIT) and Health Insurance Portability And Accountability Act (HIPAA) frameworks

C.

Frameworks specific to the industries and locations clients do business in

D.

National Institute Of Standards And Technology and International Organization For Standardization (ISO) frameworks

Question 175

A company’s Marketing and Sales departments have identified an opportunity to develop a new market for a product family and requested an increase in the production plan. Which of the following actions would be most appropriate to account for the new market opportunity?

Options:

A.

Increase the production plan as requested.

B.

Regenerate the material requirements plan.

C.

Regenerate the master production schedule (MPS).

D.

Present the proposal at the executive sales and operations (S&OP) meeting.