Project and Change Management Questions and Answers

Question 5

Leo is a well-loved middle manager at a financial organisation. He has been selected to lead a Change Project as the senior leadership team are confident that he will be able to motivate others within the company of the need for change. What type of power is Leo likely to hold?

Options:

A.

positional

B.

expert

C.

personal

D.

negative

Question 6

Ali is a Project Manager at a large retail organisation within the UK. He has created a project timeline and allocated a budget. However, two months into the project the UK declares a national lockdown due to an unknown virus sweeping the nation. What type of complexity is this known as?

Options:

A.

structural complexity

B.

technical complexity

C.

directional complexity

D.

temporal complexity

Question 7

Why would a project use aProject Baseline?

Options:

A.

it holds Project Managers to account

B.

it provides an optimal model for how the project should run

C.

it ensures sign-off of the Project Initiation Document

D.

it provides a framework of KPIs

Question 8

Which of the following questions could be answered by arisk simulation softwaresuch asMonte Carlo?Select TWO

Options: